Journal Call no. | TL726.7.H6P763 |
---|---|
Article Title | Passenger terminal 'moves' towards April '98. |
Is Part Of | Airport Authority Hong Kong news ; no.4, Oct 1996, p.4-5, illus. |
Abstract | Construction of the new airport passenger terminal began in April 1995 and, in just under 18 months, structural works have given way to the installation of skylights in the roof, mullions and glazing, and exterior cladding. According to the Airport Authority's Project Manager for Electrical and Mechanical Works, Mr Tsui King-cheong, the terminal building superstructure is virtually complete, their priority is installation of services, systems and finishings. |